Aecom Technology will provide construction-management services at the nitrogen removal facilities at the city’s 370-million-gallon-per-day Blue Plains Advanced Wastewater Treatment Plant. The construction projects included in the approximately US$300-million Enhanced Nitrogen Removal Program involve enhanced nitrogen-removal facilities, centrate-treatment facilities, Phase II gravity-thickener upgrades, plant-wide fine-bubble aeration and several other smaller projects.
This latest contract follows the recent award of a US$19.5 million supplement to Aecom Technology's Nitrogen Removal Program Management contract at the plant.
The project is scheduled for completion in 2016.